Infrastructure technique
With a strong vision and potential, the infrastructure in Viet Hung Industrial Park is being well and modernly invested by Thanh Cong Group, aiming to form a professional, advanced, environment-friendly and sustainable development industrial park.
The technical infrastructure system in Viet Hung Industrial Park is implementing a complete and synchronized themselves, ensuring the necessary conditions to attract second-party investors.
Power supply system
3x63MVA – 110/220KV substation, 22 KV power line built along the internal road of the industrial park.
3×63 MVA – 110/220 KV

Water Supply System
There is an agreement to connect with Dong Ho water supply plant (20,000 m3/day). The water supply pipe system is a closed circuit along the internal road of the industrial park.
20,000m3/day

Sewage Treatment Plant
Capacity 2×3000 m3/day, wastewater treatment ensures the output quality of Column A, QCVN 40: 2011 / BTNMT.
2×3000 m3/day

Telecommunications infrastructure
Modern information system meets international standards, fully meets domestic and foreign communication services, with multimedia, internet, IP phone services.
The system is underground and has connection distribution points.


Fire prevention and fighting
The fire water supply system is arranged along the roads, the distance between the fire pillars is from 120 m – 150 m


Drainage system
Separate construction of rainwater and sewage. Running along the industrial park is a 9m wide open ditch, ensuring rainwater drainage and creating landscape